Login

 

Forgot password?
submarines shipbuilding Black Sea Fleet exercise Pacific Fleet Russian Navy Northern Fleet strategy cooperation Ukraine visits Russia piracy missiles trials Sevastopol history Sevmash presence contracts drills Baltic Fleet industry incident anti-piracy shipyards training Gulf of Aden frigate Somalia India developments reforms opinion Borei policy procurements Russia - India aircraft carrier Crimea arms exports USA St. Petersburg France financing tests Bulava Yury Dolgoruky Serdiukov US Navy Mediterranean cruise Zvezdochka NATO innovations Indian Navy United Shipbuilding Corporation Medvedev Arctic agreements commission Admiralteyskie Verfi Admiral Gorshkov Mistral Vladivostok accident hijacking corvettes overhaul Russia - France anniversary Admiral Kuznetsov Vysotsky Rosoboronexport event ceremony Yantar Severomorsk negotiations defense order conflict aircraft China deployment naval aviation Black Sea Putin investigations Varyag coast guard Vikramaditya Novorossiysk landing craft Far East marines crime Severnaya Verf meeting scandals memorials Syria traditions Japan escort South Korea statistics Yasen Neustrashimy tenders convoys Admiral Chabanenko Marshal Shaposhnikov Ukrainian Navy Chirkov problems Severodvinsk reinforcement tension technology tragedy firings provocation Caspian Flotilla frontier service upgrade Baltic Sea hostages search and rescue Almaz Moskva court rumors Turkey Dmitry Donskoy keel laying helicopters Kilo class World War II death Kaliningrad shipwreck Petr Veliky Admiral Panteleyev Atalanta Rubin Admiral Vinogradov Norway launching delivery patrols
Search
Our friends russian navy weapons world sailing ships
 
Tell a friend Print version

Yantar shipyard started mooring trials of the first Indian frigate

Yantar shipyard started mooring trials of the first Indian frigate 05.03.2011
Text: Vesti.Ru
Photo: Project 11356 frigate. Yantar shipyard
Mooring trials of the first Indian frigate started at Yantar shipyard (Kaliningrad). All shipborne systems will be tested during a 2-month stay at the shipyard quay.

The ship announced her birth with a loud siren. First tentatively nodding and then self-confidently bowing barrels of AK-630 rapid-fire gun, the ship complimented her creators. Although mooring trials is not a sortie yet, but almost all workers of assembling shop came to watch the ship's first moves.

Four years of construction have been left behind. There was an array of problems – lack of financing, misunderstanding with equipment suppliers, deficiency of qualified workers. All that things had negative impact on the shipbuilding schedule. But at last the ship is almost completed.

Today the work is humming in all compartments, in pilot room, in commanding officer's battle station.

Representatives of all supplying companies arrived to Yantar from all across Russia to assemble and adjust the equipment. Most of systems have been already put into operation, although pre-start adjustments have not been completed so far.

The ship must be ready for fueling by the end of March; after that, trial runs of diesel generators and main propulsion units will be held. Sea trials are going to start in May; the frigate is planned to be delivered in September.

Back to the list





Back to news list