submarines shipbuilding Black Sea Fleet exercise Pacific Fleet Russian Navy Northern Fleet strategy cooperation Ukraine visits Russia piracy missiles trials Sevastopol history Sevmash presence contracts drills Baltic Fleet industry incident anti-piracy shipyards Gulf of Aden frigate training Somalia India developments reforms opinion Borei procurements policy Russia - India aircraft carrier Crimea arms exports USA St. Petersburg France tests financing Bulava Yury Dolgoruky US Navy Serdiukov cruise Mediterranean Zvezdochka NATO innovations United Shipbuilding Corporation Indian Navy Medvedev Arctic agreements commission Admiralteyskie Verfi Admiral Gorshkov Vladivostok Mistral accident hijacking corvettes overhaul Admiral Kuznetsov anniversary Russia - France Vysotsky Rosoboronexport ceremony event Yantar Severomorsk negotiations defense order conflict aircraft China deployment naval aviation investigations Black Sea Putin Varyag coast guard Novorossiysk Vikramaditya landing craft crime Far East marines Severnaya Verf meeting scandals memorials traditions Syria statistics Japan escort South Korea Yasen Neustrashimy tenders Marshal Shaposhnikov Admiral Chabanenko convoys Ukrainian Navy problems Severodvinsk Chirkov reinforcement tension firings tragedy technology Baltic Sea search and rescue Almaz Moskva frontier service Caspian Flotilla provocation hostages upgrade court Dmitry Donskoy keel laying rumors Turkey World War II death shipwreck Admiral Panteleyev Atalanta Petr Veliky helicopters Kilo class Kaliningrad Admiral Vinogradov Norway Rubin delivery launching patrols
Search
Our friends russian navy weapons world sailing ships
 
Tell a friend Print version

First Sortie of INS Vikramaditya Postponed For May 2012

First Sortie of INS Vikramaditya Postponed For May 2012 29.09.2011
Text: RusNavy.com
Photo: INS Vikramaditya. solid-msk.ru
As a result of inspection held by top-ranking Indian officers at Sevmash shipyard, general schedule of modernization works on aircraft carrier INS Vikramaditya was revised.

As was earlier reported by Central Navy Portal, delegation of Indian Navy officers headed by chief of ship building and procurement department Vice Admiral N.N. Kumar arrived at JSC Sevmash shipyard on Sept 20. Main result of the inspection was changing of pre-scheduled start date of Vikramaditya's sea trials.

Military cooperation with India has been always one of Russia's top priorities. This time, Indian delegation was met by a group of high-ranking persons headed by president of JSC United Shipbuilding Corporation (USC) Roman Trotsenko and leadership of Sevmash shipyard – acting director general Mikhail Budnichenko and chief engineer Alexei Alsufiev, vice president of USC and director general of Northern Shipbuilding and Ship Repair Center Anatoly Tiukov, head of military technical cooperation department Igor Ponomariov, deputy chief of Rosoboronexport's Navy department Evgeny Odintsov.

Summarizing results of inspection, the parties signed a working protocol. Indian Navy's delegates were satisfied with the course of works on the ship's upgrade and agreed with Sevmash officials to postpone the start date of sea trials from Dec 2011 to May 2012 without delaying of the full trial program providing that the acceptance certificate would be signed in due time – on Dec 4, 2012.

According to the protocol, although the works are 4 months behind the schedule, Russian party obliged to do away with the lag till the beginning of sea trials, i.e. end of May, 2011. As of today, the ship is 85% ready. Sevmash will have to complete basic outfitting works, interior finishing, and mooring trials until March 2012. Electromagnetic field measurements are scheduled in Apr 2012, and upon their results it will be decided whether the ship needs degaussing. Till 2012 the shipyard will have to furnish messrooms, cookrooms, medical and living premises: cabins, crew quarters, shower rooms and latrines. Besides, the ship must be checked by Navigation Safety Inspection, and one of its obligatory conditions is that the trial crew should settle in the ship at least 90 days prior to the first sortie. Thus, settlement date of Russian crew to INS Vikramaditya must be mid-Feb 2012.

VADM Kumar drew attention to a number of other problems, such as training of Indian crew, transfer of service documentation, etc. Generally, the Indian party had noticed considerable progress. The next inspection is to arrive at Sevmash in Jan 2012 to check trials of main propulsion plant.