submarines shipbuilding Black Sea Fleet exercise Pacific Fleet Russian Navy Northern Fleet strategy cooperation Ukraine visits Russia piracy missiles trials Sevastopol history Sevmash presence contracts drills Baltic Fleet industry incident anti-piracy shipyards Gulf of Aden frigate training Somalia India developments reforms opinion Borei procurements policy Russia - India aircraft carrier Crimea arms exports USA St. Petersburg France tests financing Bulava Yury Dolgoruky US Navy Serdiukov cruise Mediterranean Zvezdochka NATO innovations United Shipbuilding Corporation Indian Navy Medvedev Arctic agreements commission Admiralteyskie Verfi Admiral Gorshkov Vladivostok Mistral accident hijacking corvettes overhaul Admiral Kuznetsov anniversary Russia - France Vysotsky Rosoboronexport ceremony event Yantar Severomorsk negotiations defense order conflict aircraft China deployment naval aviation investigations Black Sea Putin Varyag coast guard Novorossiysk Vikramaditya landing craft crime Far East marines Severnaya Verf meeting scandals memorials traditions Syria statistics Japan escort South Korea Yasen Neustrashimy tenders Marshal Shaposhnikov Admiral Chabanenko convoys Ukrainian Navy problems Severodvinsk Chirkov reinforcement tension firings tragedy technology Baltic Sea search and rescue Almaz Moskva frontier service Caspian Flotilla provocation hostages upgrade court Dmitry Donskoy keel laying rumors Turkey World War II death shipwreck Admiral Panteleyev Atalanta Petr Veliky helicopters Kilo class Kaliningrad Admiral Vinogradov Norway Rubin delivery launching patrols
Search
Our friends russian navy weapons world sailing ships
 
Tell a friend Print version

Delivery Date of SSBN Verkhoturye Determined

Delivery Date of SSBN Verkhoturye Determined 20.12.2011
Text: RusNavy.com
Photo: SSBN K-51 Verkhoturye. podlodka.su
Project 667BDRM nuclear-powered ballistic missile submarine (SSBN) Verkhoturye which is currently being repaired on the main slipway of JSC Zvezdochka Ship Repair Center will be delivered to the Navy by the end of 2012, reports the yard's press service.

The submarine is supposed to leave the covered slipway in March 2012. After that, nuclear reactor cores will be refueled. By that time, floating workshop PM-63 will be ready to perform this technologically complicated process. Before the sub is placed in the dock, shipbuilders of Zvezdochka will perform an array of works, i.e. assembling of the dock equipment, reactor refueling systems, and damage control systems. Also, access patch of the strength hull must be placed and welded in the 3-rd section.

To meet the deadline, the shipyard will have to work in the New Year holidays. It is planned to use repairing experience of SSBN Karelia in order to reduce time of the dock operations. For instance, experts of Severny Reid will adjust navigation system Shluz inside the covered slipway before the sub's withdrawal.

SSBN Verkhoturye is not a young submarine; she was built in 1984 and passed interim overhaul at Zvezdochka in 1993-1998 in the times of persistent underfinancing. Old equipment from utilized subs was mounted instead of new one. In this regard, most of onboard systems has been rejected and need replacement. The shipyard has already spent so-called internal reserves, so it is almost impossible to deliver new equipment in a relatively short time.

In the second half of 2011, Zvezdochka shipyard and contracting companies have repaired outer and strength hulls, bulkheads, fairings, high-pressure air tanks, submergence and surfacing systems, etc.

Testing of ballast tanks has been almost completed; turbines of autonomous turbo generator, turbine-geared propulsion unit, and main condensers have been repaired; gyro room is ready for installation of Shluz navigation system. Internal tanks have been painted; battery wells are ready for battery mounting. Curiously, SPO Arktika used nonstandard solutions in order to finish repair of large-size electric machines in time. For instance, a specially designed bearing was installed in one of pumps; that made possible not to cut access holes in gas-proof coverage for taking out that large-size equipment.

JSC Askold (Far East) has carried out complicated overhaul of air system fittings, and JSC Zvezda (St. Petersburg) delivered two diesel generators.

In Sept 2011, director general of JSC Zvezdochka approved the beginning of mooring trials for particular systems. As for now, over 50 projects have been finished.