submarines shipbuilding Black Sea Fleet exercise Pacific Fleet Russian Navy Northern Fleet strategy cooperation Ukraine visits Russia piracy missiles trials Sevastopol history Sevmash presence contracts drills Baltic Fleet industry incident anti-piracy shipyards training Gulf of Aden frigate Somalia India developments reforms opinion Borei policy procurements Russia - India aircraft carrier Crimea arms exports USA St. Petersburg France tests financing Bulava Yury Dolgoruky US Navy Serdiukov Mediterranean cruise Zvezdochka NATO innovations United Shipbuilding Corporation Indian Navy Medvedev Arctic agreements commission Admiralteyskie Verfi Admiral Gorshkov Mistral Vladivostok accident hijacking corvettes overhaul Admiral Kuznetsov Russia - France anniversary Rosoboronexport Vysotsky event ceremony Yantar Severomorsk negotiations defense order conflict aircraft China deployment naval aviation Black Sea Putin investigations Varyag coast guard Vikramaditya Novorossiysk landing craft Far East marines crime Severnaya Verf meeting scandals memorials traditions Syria Japan escort South Korea statistics Neustrashimy Yasen tenders convoys Admiral Chabanenko Marshal Shaposhnikov Ukrainian Navy Chirkov problems Severodvinsk reinforcement tension tragedy technology firings provocation frontier service Caspian Flotilla hostages Baltic Sea upgrade search and rescue Almaz Moskva court rumors Dmitry Donskoy Turkey keel laying helicopters Kilo class Kaliningrad death World War II shipwreck Admiral Panteleyev Petr Veliky Atalanta Rubin Admiral Vinogradov Norway patrols Russia-Norway launching
Search
Our friends russian navy weapons world sailing ships
 
Tell a friend Print version

Interior Works in INS Vikramaditya Continue 24-7

Interior Works in INS Vikramaditya Continue 24-7 12.03.2012
Text: RusNavy.com
Photo: fotografersha.livejournal.com
Composite teams work overtime and without weekends finishing interior premises of aircraft carrier INS Vikramaditya modernized for Indian Navy by Sevmash shipyard (Severodvinsk, Russia). A special timetable was made up, and quite good recompense is paid, reports the shipyard's press service.

Shipborne furniture in over than 3,000 rooms is being assembled for three months. Finishers pay greater attention on 58 officer cabins.

To meet the schedule, the teams were enlarged; together with outside experts, contractors and auxiliary personnel, each team numbers about 40 men. Scope of furniture assemblage and sound insulation works is large. For instance, one of teams headed by foreman Ivan Kolovertov finishes 187 cabins, storage spaces, crew's quarters, battle stations, medical and cook rooms.

Works have been completed in one of construction areas; furnishing of the ship's mess rooms is also at final stage. According to Sevmash's carpentry director Evgeny Smekhov, "furniture installed in Vikramaditya is fully produced by our yard. It has been already manufactured, and the main thing now is to assemble it on time. We're doing our best to meet the production schedule".

Recall that Project 11430 aircraft carrier INS Vikramaditya (former Project 11434 Russian aircraft-carrying cruiser Admiral Gorshkov) retrofitted for Indian Navy by JSC Sevmash is supposed to be delivered to the customer not later than Dec 4, 2012. The carrier is to start sea trials on May 29, 2012.