Login

 

Forgot password?
submarines shipbuilding Black Sea Fleet exercise Pacific Fleet Russian Navy Northern Fleet strategy cooperation Ukraine visits Russia piracy missiles trials Sevastopol history Sevmash presence contracts drills Baltic Fleet industry incident anti-piracy shipyards training Gulf of Aden frigate Somalia India developments reforms opinion Borei procurements policy Russia - India aircraft carrier Crimea arms exports USA St. Petersburg tests France financing Bulava Yury Dolgoruky Serdiukov US Navy cruise Mediterranean Zvezdochka NATO innovations United Shipbuilding Corporation Indian Navy Medvedev Arctic agreements commission Admiralteyskie Verfi Admiral Gorshkov Mistral Vladivostok accident hijacking corvettes overhaul Admiral Kuznetsov anniversary Russia - France Rosoboronexport Vysotsky event ceremony Yantar Severomorsk defense order negotiations conflict aircraft China deployment naval aviation Putin investigations Black Sea Varyag coast guard Novorossiysk Vikramaditya landing craft Far East crime marines Severnaya Verf meeting scandals memorials Syria traditions South Korea Japan escort statistics Neustrashimy Yasen tenders Admiral Chabanenko convoys Marshal Shaposhnikov Ukrainian Navy Chirkov problems Severodvinsk reinforcement tension technology firings tragedy Baltic Sea frontier service Almaz search and rescue upgrade hostages Caspian Flotilla provocation Moskva court Dmitry Donskoy Turkey keel laying rumors helicopters death Kilo class shipwreck Admiral Panteleyev Atalanta World War II Petr Veliky Kaliningrad Admiral Vinogradov Norway Rubin delivery launching patrols
Search
Our friends russian navy weapons world sailing ships
 
Tell a friend Print version

INS Vikramaditya Prepares for Taking Sea

INS Vikramaditya Prepares for Taking Sea 19.04.2012
Text: RusNavy.com
Photo: Project 11430 aircraft carrier INS Vikramaditya. Press service of JSC Sevmash
Igor Leonov, construction manager of Project 11430 aircraft carrier INS Vikramaditya modernized by Sevmash shipyard for Indian Navy, told about works scheduled in April to prepare the ship for sea trials starting on May 25, reports the shipyard's press service.

According to Leonov, works planned for March have been almost completed. Final finishing of internal premises and assembling of shipborne furniture have been executed. Tanker Chaika pumped 3,600 tons of fuel into the ship. Tugs of the yard's water transport department did their job excellently and tugged the non-ice harbor tanker aboard the carrier.

Two critical issues remained uncompleted, i.e. startup of refrigerating machines and fixture of search-and-rescue equipment. The first problem needed personnel replacements, and the second one delayed for 10 days. This was because drawings of equipment fixtures did not match those on the ship, so additional works were needed.

Late in March, a contingency happened; smoke flue of one of eight boilers was damaged. The accident causes are being currently investigated. The boiler itself and charging turbine set were not damaged and are fully serviceable. Upon delivery of new expansion joints from St. Petersburg, the smoke flue will be completely repaired till sea trials begin.

On Apr 6, the ship was transferred to deperming station; all life support systems began off-line operation. Important indicator of self-sufficiency is that crew is regularly provided with hot food. One of three shipborne cookrooms was put into operation. All 360 servicemen keeping watch on the ship get three meals a day. Works on drinking water tanks go on as well; they will be treated by ozone which is the most advanced and effective method.

Since deperming works began, daily traffic flow to the ship exceeds 3,000 persons. Working and living conditions are already established. Washrooms, shower rooms, latrines, cabins for workers and crewmembers are fully-equipped and ready for use.

According to weather forecasts, night temperatures will be below zero in April. This causes additional problems to experts involved in deperming works. Early in May, it is planned to hold heeling test to calculate the ship's stability.

Then spare parts, tools and accessories will be loaded in the ship, as well as fuel and food supplies in order to maintain sea trials.

Sevmash started arranging the carrier's trials in the White Sea. De-berthing and pilotage plans have been agreed upon with White Sea Naval Base command. Fourteen tugs will be involved to provide safe departure of INS Vikramaditya.

Back to the list





Back to news list