submarines shipbuilding Black Sea Fleet exercise Pacific Fleet Russian Navy Northern Fleet strategy cooperation Ukraine visits Russia piracy missiles trials Sevastopol history Sevmash presence contracts drills Baltic Fleet industry incident anti-piracy shipyards Gulf of Aden frigate training Somalia India developments reforms opinion Borei policy procurements Russia - India aircraft carrier Crimea arms exports USA St. Petersburg tests France financing Bulava Yury Dolgoruky US Navy Serdiukov cruise Mediterranean Zvezdochka NATO innovations United Shipbuilding Corporation Indian Navy Medvedev Arctic agreements commission Admiralteyskie Verfi Admiral Gorshkov Vladivostok Mistral accident hijacking corvettes overhaul anniversary Russia - France Admiral Kuznetsov Rosoboronexport Vysotsky event ceremony Yantar Severomorsk defense order negotiations conflict aircraft China deployment naval aviation Black Sea Putin investigations Varyag coast guard Vikramaditya Novorossiysk landing craft Far East crime marines Severnaya Verf meeting scandals memorials traditions Syria statistics Japan escort South Korea Neustrashimy Yasen tenders convoys Marshal Shaposhnikov Admiral Chabanenko Ukrainian Navy Chirkov problems Severodvinsk reinforcement tension firings tragedy technology search and rescue Moskva provocation frontier service Baltic Sea Almaz upgrade hostages Caspian Flotilla court keel laying Dmitry Donskoy rumors Turkey shipwreck Petr Veliky helicopters Kilo class death Admiral Panteleyev Atalanta Kaliningrad World War II Norway Rubin Admiral Vinogradov patrols Russia-Norway delivery
Search
Our friends russian navy weapons world sailing ships
 
Tell a friend Print version

India Set Delivery Deadline for INS Vikramaditya

India Set Delivery Deadline for INS Vikramaditya 27.11.2012
Text: Lenta.ru
Photo: Press service of JSC Sevmash
Indian defense ministry named the end of 2013 as a deadline for delivery of aircraft carrier INS Vikramaditya modernized in Russia, reported Defense News referring to Indian defense minister A.K. Antony. As for him, commission of the aircraft carrier has been already delayed for 5 years. The minister did not specify whether any sanctions would be imposed on Russia in case of further delays.

The contract for aircraft carrier INS Vikramaditya (former Russian Project 11434 aircraft-carrying cruiser Admiral Gorshkov) was signed by Russia and India in 2004. Then the contract cost $1.5 bln. India received the carrier for free but paid that money only for the ship's repair and modernization, as well as air wing consisting of fighters MiG-29K/KUB and helicopters Ka-28/31. The parties revised contractual terms in 2009, and the contract cost increased up to $2.3 bln.

It was initially planned that Indian Navy would receive the ship upgraded under Project 11430 in Aug 2008, but delivery dates were postponed many times then. According to the latest agreement, the ship was supposed to arrive in India in Dec 2012, but Russia deferred the ship's delivery to the first half of 2013. The reason was failed trials of Vikramaditya in the Barents Sea when seven out of eight steam boilers broke down due to low-grade thermal insulation.

Indian authorities were planning to impose a $115-mln penalty on Russia for delayed delivery of the aircraft carrier. However, no official claims were made.