submarines shipbuilding Black Sea Fleet exercise Pacific Fleet Russian Navy Northern Fleet strategy cooperation Ukraine visits Russia piracy missiles trials Sevastopol history Sevmash presence contracts drills Baltic Fleet industry incident anti-piracy shipyards training Gulf of Aden frigate Somalia India developments reforms opinion Borei procurements policy Russia - India aircraft carrier Crimea arms exports USA St. Petersburg France financing tests Bulava Yury Dolgoruky US Navy Serdiukov cruise Mediterranean Zvezdochka NATO innovations United Shipbuilding Corporation Indian Navy Medvedev Arctic agreements commission Admiralteyskie Verfi Admiral Gorshkov Mistral Vladivostok accident hijacking corvettes overhaul anniversary Russia - France Admiral Kuznetsov Vysotsky Rosoboronexport ceremony event Yantar Severomorsk negotiations defense order conflict aircraft China deployment naval aviation Black Sea investigations Putin Varyag coast guard Novorossiysk Vikramaditya landing craft crime Far East marines meeting Severnaya Verf scandals memorials Syria traditions statistics Japan escort South Korea Yasen Neustrashimy tenders convoys Marshal Shaposhnikov Admiral Chabanenko Ukrainian Navy Chirkov problems Severodvinsk reinforcement tension firings technology tragedy hostages search and rescue upgrade Moskva Baltic Sea provocation frontier service Almaz Caspian Flotilla court keel laying Turkey Dmitry Donskoy rumors Kaliningrad shipwreck Petr Veliky World War II death helicopters Kilo class Admiral Panteleyev Atalanta Norway Rubin Admiral Vinogradov patrols delivery Russia-Norway
Search
Our friends russian navy weapons world sailing ships
 
Tell a friend Print version

2nd Mistral Warship to Be Complete in 2014 – Vice Premier

2nd Mistral Warship to Be Complete in 2014 – Vice Premier 25.06.2013
Text: RIA Novosty
Photo: defense.gouv.fr
Russia’s second Mistral-class, amphibious assault ship will be complete in October 2014, a deputy prime minister in charge of the defense industry said Sunday, adding that the first Mistral would enter the nation’s fleet this October.

Speaking live on national television network NTV, Deputy Prime Minister Dmitry Rogozin added that construction of the stern for the first such helicopter-carrying warship would finish at St. Petersburg’s Baltiisky shipyard within two or three days.

Early last week, Deputy Defense Minister Yury Borisov said the stern might not be completed within deadline, but Rogozin days later refuted that remark, saying: “The ship will be ready on time.”