submarines shipbuilding Black Sea Fleet exercise Pacific Fleet Russian Navy Northern Fleet strategy cooperation Ukraine visits Russia piracy missiles trials Sevastopol history Sevmash presence contracts drills Baltic Fleet industry incident anti-piracy shipyards training Gulf of Aden frigate Somalia India developments reforms opinion Borei policy procurements Russia - India aircraft carrier Crimea arms exports USA St. Petersburg tests France financing Bulava Yury Dolgoruky US Navy Serdiukov Mediterranean cruise Zvezdochka NATO innovations Indian Navy United Shipbuilding Corporation Medvedev Arctic agreements commission Admiralteyskie Verfi Admiral Gorshkov Mistral Vladivostok accident hijacking corvettes overhaul Admiral Kuznetsov Russia - France anniversary Vysotsky Rosoboronexport ceremony event Yantar Severomorsk defense order negotiations aircraft conflict China deployment naval aviation investigations Black Sea Putin Varyag coast guard Vikramaditya Novorossiysk landing craft Far East marines crime meeting Severnaya Verf scandals memorials Syria traditions statistics Japan South Korea escort Yasen Neustrashimy tenders Admiral Chabanenko Marshal Shaposhnikov convoys Ukrainian Navy problems Chirkov Severodvinsk reinforcement tension firings technology tragedy hostages Almaz provocation Moskva Caspian Flotilla upgrade frontier service Baltic Sea search and rescue court keel laying rumors Turkey Dmitry Donskoy shipwreck Kaliningrad Petr Veliky Admiral Panteleyev Atalanta World War II helicopters Kilo class death Norway Rubin Admiral Vinogradov patrols Russia-Norway launching
Search
Our friends russian navy weapons world sailing ships
 
Tell a friend Print version

Sevmash goes on ballasting of Prirazlomnaya ice-resistant oil platform

05/23/2011 
Text: JSC Sevmash press service
Photo: dvinainform.ru
Ballasting of Prirazlomnaya ice-resistant oil platform continues at 35th Ship Repair Plant in Murmansk.

Foundation concreting works are carried out by contracting agency JSC Germes possessing two advanced mobile concrete plants, required equipment and materials. Ballasting is performed in accordance with production schedule; over 1,000 cubic meters of concrete is loaded each day. It is planned to complete the operation in 1.5 months.

Concrete is delivered by railway; one part of it is stored for contingency cases. Composition and batch of concrete is made automatically and permanently monitored, commented deputy director general of Sevmash shipyard Valery Borodin.

Generally, scope of works increasingly grows, especially electric and assembling operations. Nevertheless, number of assembling fitters, welders and electricians must be increased.