submarines shipbuilding Black Sea Fleet exercise Pacific Fleet Russian Navy Northern Fleet strategy cooperation Ukraine visits Russia piracy missiles trials Sevastopol history Sevmash presence contracts drills Baltic Fleet industry incident anti-piracy shipyards training Gulf of Aden frigate Somalia India developments reforms opinion Borei policy procurements Russia - India aircraft carrier Crimea arms exports USA St. Petersburg France tests financing Bulava Yury Dolgoruky US Navy Serdiukov Mediterranean cruise Zvezdochka NATO innovations United Shipbuilding Corporation Indian Navy Medvedev Arctic agreements commission Admiralteyskie Verfi Admiral Gorshkov Mistral Vladivostok accident hijacking corvettes overhaul Admiral Kuznetsov Russia - France anniversary Rosoboronexport Vysotsky event ceremony Yantar Severomorsk negotiations defense order conflict aircraft China deployment naval aviation Black Sea Putin investigations Varyag coast guard Vikramaditya Novorossiysk landing craft Far East marines crime Severnaya Verf meeting scandals memorials traditions Syria Japan escort South Korea statistics Neustrashimy Yasen tenders convoys Admiral Chabanenko Marshal Shaposhnikov Ukrainian Navy Chirkov problems Severodvinsk reinforcement tension tragedy technology firings provocation frontier service Caspian Flotilla hostages Baltic Sea upgrade search and rescue Almaz Moskva court rumors Dmitry Donskoy Turkey keel laying helicopters Kilo class Kaliningrad death World War II shipwreck Admiral Panteleyev Petr Veliky Atalanta Rubin Admiral Vinogradov Norway patrols Russia-Norway launching
Search
Our friends russian navy weapons world sailing ships
 
Tell a friend Print version

New joint venture was set to construct shipyard on Kotlin Island

06/27/2011 
Text: RusNavy.com
Photo: Novoadmiralteyskaya Verf layout.
To construct the largest shipbuilding complex on Kotlin Island (Kronshtadt, St. Petersburg), JSC United Shipbuilding Corporation (USC) on June 16 signed an agreement with South Korean STX to establish joint venture Novoadmiralteyskaya Verf.

Reportedly, share of South Korean party in the project is 25%, overall cost is evaluated as $720 mln.

As was earlier reported, on June 17 at the St. Petersburg International Economic Forum an agreement was signed between the city administration, USC, and Admiralteyskie Verfi shipyard providing transfer of shipbuilding capacities to new site. Construction of the new shipyard would take about 40 months.

Somewhat 3 ha lands will be cleared on Admiralteysky Island to start construction of Novo-Admiralteysky Bridge.

In total, transfer of Admiralteyskie Verfi capacities will cost RUR 3.5 bln. The city will compensate about RUR 1 bln; other RUR 2.5 bln will be taken from sale of the released area. It is planned to put the land plot for tender in the current year.

As was reported, the new shipyard would occupy about 250 ha with an access to deep channel. The yard is supposed to open new 6,500 work positions.

Novoadmiralteyskaya Verf will be capable to build ships with displacement up to 200,000 tons.