submarines shipbuilding Black Sea Fleet exercise Pacific Fleet Russian Navy Northern Fleet strategy cooperation Ukraine visits Russia piracy missiles trials Sevastopol history Sevmash presence contracts drills Baltic Fleet industry incident anti-piracy shipyards training Gulf of Aden frigate Somalia India developments reforms opinion Borei policy procurements Russia - India aircraft carrier Crimea arms exports USA St. Petersburg tests France financing Bulava Yury Dolgoruky US Navy Serdiukov cruise Mediterranean Zvezdochka NATO innovations United Shipbuilding Corporation Indian Navy Medvedev Arctic agreements commission Admiralteyskie Verfi Admiral Gorshkov Vladivostok Mistral accident hijacking corvettes overhaul Russia - France Admiral Kuznetsov anniversary Rosoboronexport Vysotsky event ceremony Yantar Severomorsk defense order negotiations conflict aircraft China deployment naval aviation Putin investigations Black Sea Varyag coast guard Vikramaditya Novorossiysk landing craft Far East crime marines Severnaya Verf meeting scandals memorials Syria traditions Japan escort South Korea statistics Neustrashimy Yasen tenders Admiral Chabanenko convoys Marshal Shaposhnikov Ukrainian Navy Chirkov problems Severodvinsk reinforcement tension tragedy technology firings provocation frontier service Baltic Sea Almaz upgrade hostages search and rescue Caspian Flotilla Moskva court Dmitry Donskoy rumors Turkey keel laying helicopters Kilo class death Admiral Panteleyev Atalanta Kaliningrad World War II shipwreck Petr Veliky Rubin Admiral Vinogradov Norway launching delivery patrols
Search
Our friends russian navy weapons world sailing ships
 
Tell a friend Print version

Second phase of Prirazlomnaya oil platform construction is over

08/17/2011 
Text: Sevmash Shipyard Press Service
Photo: sevmash.ru
Second construction phase of unique offshore ice-resistant fixed platform Prirazlomnaya has been finished; the platform leaves Murmansk. The solemn meeting was arranged at 35th Ship Repair Plant.

The platform was transferred to 35th Ship Repair Plant in Nov 2010 after construction phase in Severodvinsk. Enormous scope of work has been done in Murmansk through 9 months – concrete ballasting, precommission operations, etc. "On percentage, the platform is 94.2% ready, but there are still much to do with cable connection, adjustment works and so", comments Valery Borodin, Deputy Director General of Sevmash shipyard. "We have completed basic life support systems, i.e. made the platform habitable".

"Today we have finished a very important stage in the platform construction process", said Director General of Sevmash Andrei Dyachkov. "This day is equally significant for the shipyard staff, designers, and the orderer. Thanks to our joint dedicated work, we have achieved such good result", he concluded. "We have passed steep and toilsome ways, but finally constructed this unique asset", said Alexander Mandel, Director General of JSC Gazprom Oil Shelf which is the platform's orderer. "And the most important thing is that Russian shipbuilding industry has acquired wide experience which will be undoubtedly in demand", added the orderer.

In the nearest term Prirazlomnaya platform will head for the same-named oil field in Pechora Bay to extract oil for at least 25 years in severe climatic conditions at temperatures up to -50C.

As is planned, transportation of the platform would take somewhat 10 days, and if weather conditions are favorable it would reach the site. According to the orderer's plans, Prirazlomnaya platform would start to produce oil in the first quarter of 2012.