submarines shipbuilding Black Sea Fleet exercise Pacific Fleet Russian Navy Northern Fleet strategy cooperation Ukraine visits Russia piracy missiles trials Sevastopol history Sevmash presence contracts drills Baltic Fleet industry incident anti-piracy shipyards training Gulf of Aden frigate Somalia India developments reforms opinion Borei policy procurements Russia - India aircraft carrier Crimea arms exports USA St. Petersburg France financing tests Bulava Yury Dolgoruky Serdiukov US Navy Mediterranean cruise Zvezdochka NATO innovations Indian Navy United Shipbuilding Corporation Medvedev Arctic agreements commission Admiralteyskie Verfi Admiral Gorshkov Mistral Vladivostok accident hijacking corvettes overhaul Russia - France Admiral Kuznetsov anniversary Rosoboronexport Vysotsky event ceremony Yantar Severomorsk defense order negotiations aircraft conflict China deployment naval aviation Putin Black Sea investigations Varyag coast guard Novorossiysk Vikramaditya landing craft Far East crime marines Severnaya Verf meeting scandals memorials traditions Syria Japan escort South Korea statistics Yasen Neustrashimy tenders Admiral Chabanenko convoys Marshal Shaposhnikov Ukrainian Navy problems Severodvinsk Chirkov reinforcement tension tragedy firings technology Baltic Sea frontier service provocation Almaz hostages Caspian Flotilla search and rescue Moskva upgrade court Dmitry Donskoy rumors keel laying Turkey World War II death helicopters Kilo class Admiral Panteleyev Atalanta Kaliningrad shipwreck Petr Veliky Admiral Vinogradov Rubin Norway patrols launching Russia-Norway
Search
Our friends russian navy weapons world sailing ships
 
Tell a friend Print version

Strenuous Work Continues on Yantar Research Ship

03/30/2012 
Text: RusNavy.com
JSC Yantar Shipyard (Kaliningrad, Russia) works hard on construction of same-named Project 22010 oceanographic research ship. It is planned to maintain such working speed till the end of 2012 when the ship will be put afloat for outfitting and trials, reports the shipyard's press service.

To determine organizational and technical arrangements in order to meet contractual commitments in time, directors of all companies participating in the ship's construction convened at Yantar Shipyard in March 13-14. The ordering party was represented by VADM A. Burilichev, chief of Deepwater Research Dept at Russian Defense Ministry. He gave a good mark to works performed by the shipyard. It should be noted that research ships Yantar and Seliger also outfitted at the yard are lead ships, so their construction is any kind but simple and goes on with delay. To meet the schedule, Kaliningrad shipwrights will have to endeavor best efforts.

At present, the ship's thrusting propellers are being prepared for installation; according to plan, rudder propellers are to be mounted in April. Experts of JSC Era have already started to assemble fitter items; cable laying works are to begin soon as well. The shipyard's workshops are completing sections of the eighth block; it will be transferred to the slipway in April. Mounting of the block will close the deck erection process. Early in Jan 2012, shipbuilders held complicated technological operation jointing the ship's sections.

Estimated delivery term is the end of 2012.