submarines shipbuilding Black Sea Fleet exercise Pacific Fleet Russian Navy Northern Fleet strategy cooperation Ukraine visits Russia piracy missiles trials Sevastopol history Sevmash presence contracts drills Baltic Fleet industry incident anti-piracy shipyards frigate training Gulf of Aden Somalia India developments reforms opinion Borei procurements policy Russia - India aircraft carrier Crimea arms exports USA St. Petersburg France financing tests Bulava Yury Dolgoruky Serdiukov US Navy Mediterranean cruise Zvezdochka NATO innovations Indian Navy United Shipbuilding Corporation Medvedev Arctic agreements commission Admiralteyskie Verfi Admiral Gorshkov Mistral Vladivostok accident hijacking corvettes overhaul Admiral Kuznetsov anniversary Russia - France Rosoboronexport Vysotsky ceremony event Yantar Severomorsk defense order negotiations aircraft conflict China deployment naval aviation Putin Black Sea investigations Varyag coast guard Vikramaditya Novorossiysk landing craft crime Far East marines meeting Severnaya Verf scandals memorials Syria traditions South Korea Japan escort statistics Neustrashimy Yasen tenders Marshal Shaposhnikov Admiral Chabanenko convoys Ukrainian Navy problems Severodvinsk Chirkov reinforcement tension firings technology tragedy Baltic Sea Moskva frontier service Almaz upgrade search and rescue Caspian Flotilla hostages provocation court Dmitry Donskoy Turkey keel laying rumors death helicopters Kilo class Admiral Panteleyev Atalanta World War II shipwreck Petr Veliky Kaliningrad Admiral Vinogradov Norway Rubin launching patrols Russia-Norway
Search
Our friends russian navy weapons world sailing ships
 
Tell a friend Print version

After-Fire Recovery of SSBN Yekaterinburg Needs Two Years

06/18/2012 
Text: World Arms Trade Analytic Center.com
Photo: SSBN Yekaterinburg. reuters.com
Repair of nuclear-powered ballistic missile submarine (SSBN) Yekaterinburg suffered fire in Dec 2011 will start on June 21 at JSC Zvezdochka Ship Repair Center and last up to the middle of 2014, reports RIA Novosti referring to a source in the shipyard.

According to the source, SSBN Yekaterinburg (Project 667BDRM Delfin) will arrive at the yard on June 21. "Through the next two years, the sub's technical availability will be recovered; it is also planned to carry out emergency repairs of sonar system damaged by fire", reports the news agency.

The source of RIA Novosti said that "recovery works on Yekaterinburg were supposed to start in Dec 2011, but due to the fire repair was postponed for June 2012".

"After thorough examination of the sonar system, experts decided not to replace it but repair which is considerably cheaper", pointed out the interviewee.

Upon termination of the all-up repairs, the sub will stay in service at least till 2018, reports RIA Novosti.