submarines shipbuilding Black Sea Fleet exercise Pacific Fleet Russian Navy Northern Fleet strategy cooperation Ukraine visits Russia piracy missiles trials Sevastopol history Sevmash presence contracts drills Baltic Fleet industry incident anti-piracy shipyards frigate training Gulf of Aden Somalia India developments reforms opinion Borei procurements policy Russia - India aircraft carrier Crimea arms exports USA St. Petersburg France tests financing Bulava Yury Dolgoruky US Navy Serdiukov cruise Mediterranean Zvezdochka NATO innovations United Shipbuilding Corporation Indian Navy Medvedev Arctic agreements commission Admiral Gorshkov Admiralteyskie Verfi Mistral Vladivostok accident hijacking corvettes overhaul Admiral Kuznetsov Russia - France anniversary Vysotsky Rosoboronexport event ceremony Yantar Severomorsk negotiations defense order conflict aircraft China deployment naval aviation investigations Black Sea Putin Varyag coast guard Novorossiysk Vikramaditya landing craft Far East crime marines meeting Severnaya Verf scandals memorials traditions Syria Japan statistics escort South Korea Neustrashimy Yasen tenders Marshal Shaposhnikov Admiral Chabanenko convoys Ukrainian Navy Severodvinsk Chirkov problems reinforcement tension firings tragedy technology Moskva search and rescue frontier service Baltic Sea Almaz provocation hostages upgrade Caspian Flotilla court Dmitry Donskoy rumors Turkey keel laying helicopters shipwreck Kilo class death Petr Veliky Admiral Panteleyev Atalanta Kaliningrad World War II Admiral Vinogradov Norway Rubin delivery launching patrols
Search
Our friends russian navy weapons world sailing ships
 
Tell a friend Print version

Research Ship Yantar to Put Afloat on December 5

11/27/2012 
Text: RusNavy.com
Photo: sdelanounas.ru
Launching ceremony of research ship Yantar being built in Kaliningrad for Russian Navy will be held on Dec 5, a source in shipbuilding industry told Central Navy Portal.

Project 22010 oceanographic research ship Yantar was laid down in July 2010. It was initially planned to put the ship afloat in mid Nov 2012, but due to delays in construction the deadline was postponed.

As for now, central switchboard was mounted on the ship; electrical installation works have been partially completed. The research ship Yantar was laid down on the 65-th anniversary of JSC Yantar Shipyard (Kaliningrad, Russia) and was named in the shipyard's honor. She is the largest ship currently built at the yard.

The ship was painted in mid Nov; works on stretching cable lines, planting of fittings and various mechanisms are in progress. About 150 shipwrights and representatives of contracting parties are working day and night to prepare the ship for launching.

"Such specific ship is unusual for the shipyard, so the building process goes behind the schedule. Moreover, there are some frustrations in delivery of associated equipment", a source in United Shipbuilding Corporation told Central Navy Portal. "It is planned to begin dockside trials in the coming summer, and then to hold sea trials. If everything is okay, the ship would be possibly handed over to defense ministry by the year end", the source added.