submarines shipbuilding Black Sea Fleet exercise Pacific Fleet Russian Navy Northern Fleet strategy cooperation Ukraine visits Russia piracy missiles trials Sevastopol history Sevmash presence contracts drills Baltic Fleet industry incident anti-piracy shipyards training Gulf of Aden frigate Somalia India developments reforms opinion Borei policy procurements Russia - India aircraft carrier Crimea arms exports USA St. Petersburg France financing tests Bulava Yury Dolgoruky Serdiukov US Navy Mediterranean cruise Zvezdochka NATO innovations Indian Navy United Shipbuilding Corporation Medvedev Arctic agreements commission Admiralteyskie Verfi Admiral Gorshkov Mistral Vladivostok accident hijacking corvettes overhaul Russia - France Admiral Kuznetsov anniversary Rosoboronexport Vysotsky event ceremony Yantar Severomorsk defense order negotiations aircraft conflict China deployment naval aviation Putin Black Sea investigations Varyag coast guard Novorossiysk Vikramaditya landing craft Far East crime marines Severnaya Verf meeting scandals memorials traditions Syria Japan escort South Korea statistics Yasen Neustrashimy tenders Admiral Chabanenko convoys Marshal Shaposhnikov Ukrainian Navy problems Severodvinsk Chirkov reinforcement tension tragedy firings technology Baltic Sea frontier service provocation Almaz hostages Caspian Flotilla search and rescue Moskva upgrade court Dmitry Donskoy rumors keel laying Turkey World War II death helicopters Kilo class Admiral Panteleyev Atalanta Kaliningrad shipwreck Petr Veliky Admiral Vinogradov Rubin Norway patrols launching Russia-Norway
Search
Our friends russian navy weapons world sailing ships
 
Tell a friend Print version

Research Ship Yantar to Put Afloat on December 5

11/27/2012 
Text: RusNavy.com
Photo: sdelanounas.ru
Launching ceremony of research ship Yantar being built in Kaliningrad for Russian Navy will be held on Dec 5, a source in shipbuilding industry told Central Navy Portal.

Project 22010 oceanographic research ship Yantar was laid down in July 2010. It was initially planned to put the ship afloat in mid Nov 2012, but due to delays in construction the deadline was postponed.

As for now, central switchboard was mounted on the ship; electrical installation works have been partially completed. The research ship Yantar was laid down on the 65-th anniversary of JSC Yantar Shipyard (Kaliningrad, Russia) and was named in the shipyard's honor. She is the largest ship currently built at the yard.

The ship was painted in mid Nov; works on stretching cable lines, planting of fittings and various mechanisms are in progress. About 150 shipwrights and representatives of contracting parties are working day and night to prepare the ship for launching.

"Such specific ship is unusual for the shipyard, so the building process goes behind the schedule. Moreover, there are some frustrations in delivery of associated equipment", a source in United Shipbuilding Corporation told Central Navy Portal. "It is planned to begin dockside trials in the coming summer, and then to hold sea trials. If everything is okay, the ship would be possibly handed over to defense ministry by the year end", the source added.