submarines shipbuilding Black Sea Fleet exercise Pacific Fleet Russian Navy Northern Fleet strategy cooperation Ukraine visits Russia piracy missiles trials Sevastopol history Sevmash presence contracts drills Baltic Fleet industry incident anti-piracy shipyards training Gulf of Aden frigate Somalia India developments reforms opinion Borei policy procurements Russia - India aircraft carrier Crimea arms exports USA St. Petersburg tests France financing Bulava Yury Dolgoruky US Navy Serdiukov cruise Mediterranean Zvezdochka NATO innovations United Shipbuilding Corporation Indian Navy Medvedev Arctic agreements commission Admiralteyskie Verfi Admiral Gorshkov Vladivostok Mistral accident hijacking corvettes overhaul Russia - France Admiral Kuznetsov anniversary Rosoboronexport Vysotsky event ceremony Yantar Severomorsk defense order negotiations conflict aircraft China deployment naval aviation Putin investigations Black Sea Varyag coast guard Vikramaditya Novorossiysk landing craft Far East crime marines Severnaya Verf meeting scandals memorials Syria traditions Japan escort South Korea statistics Neustrashimy Yasen tenders Admiral Chabanenko convoys Marshal Shaposhnikov Ukrainian Navy Chirkov problems Severodvinsk reinforcement tension tragedy technology firings provocation frontier service Baltic Sea Almaz upgrade hostages search and rescue Caspian Flotilla Moskva court Dmitry Donskoy rumors Turkey keel laying helicopters Kilo class death Admiral Panteleyev Atalanta Kaliningrad World War II shipwreck Petr Veliky Rubin Admiral Vinogradov Norway launching delivery patrols
Search
Our friends russian navy weapons world sailing ships
 
Tell a friend Print version

Research Ship Yantar to Put Afloat on December 5

11/27/2012 
Text: RusNavy.com
Photo: sdelanounas.ru
Launching ceremony of research ship Yantar being built in Kaliningrad for Russian Navy will be held on Dec 5, a source in shipbuilding industry told Central Navy Portal.

Project 22010 oceanographic research ship Yantar was laid down in July 2010. It was initially planned to put the ship afloat in mid Nov 2012, but due to delays in construction the deadline was postponed.

As for now, central switchboard was mounted on the ship; electrical installation works have been partially completed. The research ship Yantar was laid down on the 65-th anniversary of JSC Yantar Shipyard (Kaliningrad, Russia) and was named in the shipyard's honor. She is the largest ship currently built at the yard.

The ship was painted in mid Nov; works on stretching cable lines, planting of fittings and various mechanisms are in progress. About 150 shipwrights and representatives of contracting parties are working day and night to prepare the ship for launching.

"Such specific ship is unusual for the shipyard, so the building process goes behind the schedule. Moreover, there are some frustrations in delivery of associated equipment", a source in United Shipbuilding Corporation told Central Navy Portal. "It is planned to begin dockside trials in the coming summer, and then to hold sea trials. If everything is okay, the ship would be possibly handed over to defense ministry by the year end", the source added.